The critical path of a network is the A. path with the fewest activities. B. path with the most activities. C. shortest time path through the network. D. longest time path through the network.

Respuesta :

uzamamanzoor1271996 uzamamanzoor1271996
  • 24-02-2020

Answer:

D is correct option

Explanation:

D. longest time path through the network.

The sequence of activities within the network with zero total float is called critical path.

Answer Link

Otras preguntas

Solve for x. −2 = 3/9x
Help needed ASAP thanks :)
Can some one please tell me what the geometric sequence of 2, 5, 12.5, 31.25 is?!!! I will give brainliest!!
Select every statement that is written in third person point of view. 1.Don, Kristi, and I attended the wedding last year. 2.To me, it's always seemed that Mar
An airline offers 21 daily flights between two cities. Of these flights, the number of nonstop flight, X, is three more than half the number of lights with one
History help please Topic: Satellite State Who: When: Where: How? What? Why? Answer those question for the Satellite State please
how was a successor to Muhammad chosen​
Cube shaped blocks are packed into a cube shaped storage container the edge length of the storage container is 2 1/2 feet the edge length of each blocks 1/5 the
The ____ model describes a universe where Earth is at the center
What’s the correct answer