a field can be cleared by 33 men in 15days. how many more person required if the field has to be cleared 4 days earlier?​

Respuesta :

wsookhuei
wsookhuei wsookhuei
  • 24-10-2020

Answer:

12 men

Step-by-step explanation:

33men x 15 days = the whole project

Let the men that are required be x.

33 x 15 = (15-4)x

495 = 11x

x = 45

Answer Link

Otras preguntas

If an employee at Starbucks makes 85$ for working an 8 hour shift,then how much money does she earn per hour? If she work 4 days this week, then how much money
I have a problem! please help!Please solve following math problem:60cm * 40cm * 55cm - 5 = [cm³] = [litres]
CAN SOMEONE JUST PLEASE ANSWER THIS ASAP FOR BRAINLIEST!!! A teacher writes the following product on the board: (-2x)(4x^3) = -8x^4 Jeff says that -8x^4 is a fa
what was the name of the exiled, Cuban leader that organized a new revolt against Spanish rule in Cuba?
The word ___________________ means parts per hundred.
Tania is interested in buying a $135,000 home. How big does her down payment need to be in order to avoid PMI?
Why were the Federalists in the Congress opposed to war against the British in 1812? A. They didn't support war to protect US trade rights and freedom of the
can someone please explain this t me im lost
federalist and central government
PLEASE help,will give brainliest Which of the following was considered the main role of Roman women? A. They elected magistrates. B. They passed laws. C.