contestada

Which type of control chart should be used when it is possible to have more than one mistake per​ item?
A. c​-chart
B. p​-chart
C. x​-bar chart
D. R​-chart

Respuesta :

hyderali230
hyderali230 hyderali230
  • 23-12-2020

Answer:

A. c​-chart

Explanation:

C chart is a control chart that is used to count the data like numbers of nonconformities per unit. It is used to monitor the total occurrence per unit.

In this chart, the data is collected in the sub-groups and then the data is analyze to check the defects or mistakes or nonconformities.

If there is more than one mistake per item the C- chart is the best match.

Answer Link

Otras preguntas

Locate the adverb phrase and the word or phrase it modifies. The library book was placed on the front desk.
-12(x - 12) =-9(1 + 7x)
How many states are there
Problem C Temperatures were obtained in November in a fairly arid area of Nevada. At two different sites, temperature readings were taken at a number of heights
Convert these improper fractions to mixed numbers 112 over 10 please help
Where were Washington and his army staying according to the article? Please
Jonathan watched 6 videos that were 8 minutes long. He also watched 5 minutes of ads during that time. For how long was Jonathan watching videos.
Question 2 Essay Worth 10 points) (08.02 MC) A pair of equations is shown below. y = 6x - 4 y = 5x - 3 Part A: In your own words, explain how you can solve the
The question is on the picture. Please help
John like chicken he gets 5 peices and only eats 2 how many does he have left